PAYMENT PLAN

Construction Linked Payment Plan (stilt + 34 &35 Towers)

At the time of allotment 20% of BSP less booking amount
On start of excavation at site 7.5% of BSP + 25% of EDC & IDC
On Completion of Basement Roof Slab 7.5% of BSP
On Completion of 3rd Floor Roof   Slab 5% of BSP+ 25% of EDC & IDC
On Completion of 7th Floor Roof Slab 5% of BSP
On Completion of 11th Floor Roof Slab 5% of BSP+ 25% of EDC & IDC
On Completion of 15th Floor Roof Slab 5% of BSP
On Completion of 19th Floor Roof Slab 5% of BSP+ 25% of EDC & IDC
On Completion of 23rd Floor Roof   Slab 5% of BSP
On Completion of 27th Floor Roof Slab 5% of BSP+ 50% of PLC
On Completion of 31st Floor Roof Slab 5% of BSP+ 50% of PLC
On Completion of top Floor Roof Slab 5% of BSP
On Completion of brick work 5% of BSP + 100% Car Parking
On Completion of plumbing & electrical work 5% of BSP
On Completion of flooring 5% of BSP
On the Offer of Possession 5% of BSP + 100% of (IFMS + FFC + PBC + Registration charges + Stamp Duty charges + Other charges)
Cheque in favour of “Pareena Infrastructures Pvt. Ltd.”

CLP (Stilt + 24 & 25 Floors)

   
At the time of Booking Booking Amount
At the time of allotment 20% of BSP less booking amount
On Start of excavation at site 7.5% of BSP + 25% of EDC/IDC
On completion of basement roof slab 7.5% of BSP
On completion of 3rd floor roof slab 7.5% of BSP + 25% of EDC/IDC
On completion of 7th floor roof slab 7.5% of BSP
On completion of 11th floor roof slab 7.5% of BSP + 25% of EDC/IDC
On completion of 15th floor roof slab 7.5% of BSP
On completion of 19th floor roof slab 7.5% of BSP + 25% of EDC/IDC
On completion of top floor roof slab 7.5% of BSP + 100% of PLC
On completion of brick work 5% of BSP + 100% of Car Parking
On completion of plumbing & electrical work 5% of BSP
On completion of flooring 5% of BSP
On offer of possession 5% of BSP + 100% of (IFMS + FFC + CMC
  PBC + Registration charges +
  Stamp Duty charges + Other charges)

DOWN PAYMENT PLAN (DPP)

Stages Percentage of BSP Percentage of Additional Charges
At the time of Booking Booking Amount  
On or before 60 days of Booking / On Allotment whichever is later 95% of BSP less Booking Amount 100% of (EDC & IDC + PLC + Car Parking Charges)
On offer of Possession 5% of BSP 100% of (CMC + IFMS + FFC + PBC + Other
Charges + Stamp Duty & Registration Charges)
Down Payment Rebate 10% on (85% of BSP + 100% of PLC)  

 

Subvention Plan :

Booking Amount: – 10% of COP (By The Customer)
With in 30 Day’s: – 75% of COP (By the Financial Institution)
At the time of offer of Possession: – 15% of COP (By The Customer)